Project · Maharashtra
Lemken – Nagpur: 477 kWp metal sheet rooftop solar in Maharashtra
Lemken bought the plant under CAPEX and owns it. The plant has supplied the site since Jul 2022.
- Capacity
- 477 kWp
- Installation
- Metal sheet roof
- Location
- Nagpur, Maharashtra
- Finance model
- CAPEX
Plant details
- Client
- Lemken
- Industry
- Agro
- Capacity
- 477 kWp (DC), with 350 kW (AC) of inverters
- Service
- EPC + O&M
- Commissioned
- Jul 2022
- Status
- Operational. Built and maintained by Adhvanik Energy; owned by the client.
At 477 kWp, the plant covers a sizeable share of a factory roof, usually split across a few inverters. 350 kW of inverters serve 477 kWp of modules: a DC/AC ratio of 1.36.
Since Jul 2022, the plant in Nagpur has run through several monsoons. That history is the first thing an O&M review reads. Its first weeks, in Jul 2022, were monsoon weeks.
For scale, the nearest match in capacity is Ronch Polymer – Daman (478 kWp, Dadra and Nagar Haveli and Daman and Diu). Jul 2022 also saw Plastiblends – Palsana (463 kWp, Gujarat) and Plastiblends – Palsana (223 kWp, Gujarat) commissioned. Of the Maharashtra plants on our list, Syngenta – Aurangabad was commissioned just before it and Ginni Gopal – Boisar just after.
On the location pages: Maharashtra · Nagpur. It is also listed in the full project list.
Engineering
The engineering behind a plant like Lemken – Nagpur
The 477 kWp at Lemken – Nagpur sits on metal sheet roofing. In many cases the structure is fixed through the sheet; where the owner wants a zero-leakage roof, the mounting is non-penetrating, with clamps that grip the ribs or seams or adhesive bonding of the rails.
On a long shed, a short, tidy cable route on trays, from array to inverters to LT panel, saves losses and maintenance time over the life of the plant.
Asset Connect keeps generation, irradiance and alerts in one place, and a drop in performance ratio is the first sign that a string, an inverter or the module surface needs attention.
Finance model
How the plant is paid for
The CAPEX route puts ownership with the client from the day of commissioning in Jul 2022. The plant is the owner's asset, and the owner decides how it is maintained and for how long.
We design, procure, build and commission a CAPEX plant, then hand it over. A 1-year defect liability period covers the entire installation, we handle manufacturer warranty claims, and the owner can sign an O&M contract of up to 25 years.
Nagpur
Nagpur and the agro sector
- Solar resource here
- 1,874 kWh/m² a yearAbout 1,567 kWh per kWp a year for a standard tilted system; July is the weakest month. Global Solar Atlas estimate for Nagpur; a roof plant at roof tilt differs.
- Capacity range
- 250 to 500 kWp477 kWp here. 36 plants on our list are in this range.
- Type of installation
- Metal sheet roofThe most common factory roof.
- Finance option
- CAPEXThe factory owns the plant from day one.
Besides the Lemken plant, our list has 2 other plants in Nagpur. The named sectors are agro; electrical and electronics.
The Nagpur area page lists 3 plants, with a link to each.
Across Maharashtra our list holds 44 plants in 17 towns, commissioned between 2020 and 2026.
Seed, feed and farm-equipment sites have seasonal demand, and a solar plant has to be sized for the months when power is used.
Agro works have open land around the buildings, which gives the option of a ground plant beside a roof plant.
Sector page: Agro & food processing solar. Rules for Maharashtra: solar policy.
Projects
Related plants
Also in Nagpur
- Horiba – Nagpur721 kWp · Carport · Sep 2024
- Apex Knives – Nagpur200 kWp · Metal sheet roof · Dec 2021
Elsewhere in Maharashtra
- Exotic Fruits – Nashik1,332 kWp · Metal sheet roof · Jul 2026
- Baramati Cattlefeeds – Baramati771 kWp · Metal sheet roof · Jul 2026
- FUSO Glass – Murbad926 kWp · Metal sheet roof · Jul 2026
- Ozpure – Maharashtra867 kWp · Metal sheet roof · Jul 2026
Other plants on metal sheet roofs
- Durian Industries – Palghar525 kWp · Metal sheet roof · Jun 2025
- MYK Laticrete – Indore405 kWp · Metal sheet roof · Jun 2025
- Zenith Irrigation – Nashik420 kWp · Metal sheet roof · May 2025
- Mysore Deep Perfumery – Indore266 kWp · Metal sheet roof · May 2025
Common questions
What people ask about this plant
What is the commissioning date of the Lemken – Nagpur plant?
Jul 2022. That is when the 477 kWp plant in Nagpur began supplying the site, and the generation record runs from then.
Who maintains this Nagpur plant?
Ownership sits with the client under CAPEX. We designed and built the plant, and our O&M team maintains it.
How do I find out if my roof can carry 477 kWp?
It depends on the roof or land, the load and the connection. The free 7-day feasibility study includes a roof feasibility check, the area available for installation and a financial ROI sheet for your site.
Guides and glossary
Guides and terms behind a 477 kWp plant
- CAPEX or PPA: which solar model fits your factory?Read the guide
- Metal sheet, RCC, ground mount or carport: choosing the installationRead the guide
- Reading your electricity bill: the numbers that matter for solarRead the guide
Terms used on this page
Free feasibility study
Want a 477 kWp plant on your own site?
The free 7-day study gives a site in Nagpur an ROI sheet, a policy check, roof feasibility and a budgetary quote. Expect an engineer within 48 hours.