Open access

Open access solar for loads your roof can't cover

Open access means buying solar power made elsewhere and carried to your factory over the state grid. It is for factories whose demand is larger than their roofs and land can supply, and Adhvanik Energy helps you work out whether it pays.

industrial rooftop solar commissioned
110 MWp
states
17

Is it for you

Which factories need open access, and when it makes sense

Open access suits factories with a large, steady demand, such as furnaces, compressors and continuous process lines, where even a full roof plus spare land would cover only a slice of the units used. It also suits groups with several factories in one state that want to buy from one plant.

It makes sense after the roofs and the land are used. Where the charges are high, or the state limits banking, it may not.

Adhvanik Energy has solar parks coming up in Maharashtra and Gujarat. If your factories are in one of these states, ask us about them.

Rules change often. Your state’s current position is on our solar policy pages.

The route

Follow one unit from the solar park to your meter

Each of the four stops below adds a charge or a loss, and the total decides whether it beats your DISCOM tariff.

  1. 01

    Solar plant

    Built on land with good sunshine, often in another district, sometimes in another state.

    Generation tariff
  2. 02

    Grid injection

    Power enters the state transmission or distribution network at a substation.

    Transmission chargesLosses
  3. 03

    Wheeling

    The network carries it to the substation that serves your factory.

    Wheeling chargesLosses
  4. 04

    Your plant

    Units are set against your consumption, time slot by time slot, on your DISCOM bill.

    SurchargesBanking

Structures

Captive, group captive or third-party: who owns the plant decides the charges

General framework under the Electricity Act, 2003 and the Electricity Rules, 2005. State regulations add their own conditions.
ItemCaptiveGroup captiveThird-party sale
Who owns the solar plantYou, as the consumerA company or SPV in which you and other consumers hold equityA developer, who sells you the power
Ownership and use testAt least 26% ownership, and at least 51% of the output consumed by the ownerThe same 26% and 51% tests, met by the captive users together; since March 2026 each user’s captive consumption is capped at its proportionate entitlementNone
Cross-subsidy surchargeNot levied on captive useNot levied while the captive tests are met; failing them in a year makes surcharges payable for that yearLevied at the rate your state commission sets
Your capitalThe full plantYour equity shareNone

Landed cost

The charges that decide your landed cost

Each state sets its own rates and revises them.

ChargeWhat it pays forWho sets it
Transmission chargesUse of the transmission network between the solar plant and your areaState (and central, if the power crosses states) regulators
Wheeling chargesUse of the distribution network that delivers power to your plantYour state electricity regulatory commission
LossesEnergy lost in the network on the way, deducted from the units you receiveYour state commission, as a percentage by voltage level
Cross-subsidy surchargeCompensates the DISCOM for the subsidy built into industrial tariffsYour state commission; captive use is exempt
Additional surchargeCovers DISCOM power-purchase costs stranded when consumers move to open accessYour state commission
BankingLets surplus units be used in a later time slot, for a chargeYour state’s open access regulations
Scheduling and feesApplication, metering and scheduling by the state load despatch centreYour state’s open access regulations
Landed cost, in one line
Landed cost = generation tariff + transmission and wheeling charges + surcharges + the cost of losses and banking. Open access works when that number stays below the DISCOM energy charge it replaces (demand charges on your contract demand usually continue), for the life of the contract.

Contract and operations

The contract, the paperwork and the monthly routine

An open access supply is a long contract and a continuing piece of administration, and both belong in the calculation from the start.

Day to day, someone on your side deals with registration, scheduling with the state load despatch centre, metering at both ends and the monthly energy account reconciled against your DISCOM bill. Ask who does each of these before you sign.

Points to settle in the power contract

Term and tariff
Contract length, the generation tariff and whether it changes during the term.
Contracted capacity
How much capacity or energy is reserved for you, and what happens if you use less.
Shortfall and surplus
Who pays for units that do not arrive, and what happens to units you cannot use.
Change in charges
Who carries the risk if a regulator revises transmission, wheeling or surcharge rates mid-term.
Payment security
The deposit or guarantee that backs your payments.
Aerial view of a factory with solar on its shed roofs

Where to start

Rooftop first, open access for the rest

Units from your own roofs and land are used behind the meter, so none of the charges above apply. Open access earns its place on the demand left over.

  • Open access is for loads larger than your roof can serve
  • Model both together, so neither is oversized

What we need

Four inputs for the calculation

Have these ready when the engineer calls.

Twelve months of bills

For every factory you want to supply: units, tariff category, demand charges and time-of-day slots.

Contract demand and voltage

Your sanctioned load and the voltage you take supply at decide eligibility and which charges apply.

Where your plants are

Rules and charges differ by state, so the location of each factory matters.

Your load profile

Meter data shows when you use power, which decides how much solar you can absorb without banking.

Why Adhvanik

Why start the open access question with Adhvanik

We do not have an open access project on our published list. What we bring is a calculation that treats your whole site.

Common questions

Open access: cost, eligibility, contracts and state rules

Landed cost, group captive rules, banking and what to ask before signing.

Speak with an industrial solar engineer
Is open access cheaper than our DISCOM tariff?

It can be, once every charge is added up: the generation tariff plus transmission, wheeling, surcharges, losses and banking. Where that total stays below the DISCOM energy charge it replaces for the contract term, open access saves money; demand charges usually continue. We model it for your state and tariff category.

Who is eligible for open access?

Consumers at or above a minimum contract demand, which is set in each state’s regulations. The Green Energy Open Access Rules, 2022 lowered the threshold for green power to 100 kW, and the 100 kW can be met by aggregating connections with the same DISCOM. States are adopting it at different speeds, so check the current rules in your state.

What is the difference between captive and group captive?

Under the Electricity Rules, 2005, a captive plant must be at least 26% owned by its users, who must also consume at least 51% of its output. In a group captive, several consumers meet those tests together through a shared company. Since the Electricity (Amendment) Rules of March 2026, the tests are applied to the users in aggregate, and each user’s captive consumption is capped at its proportionate entitlement; anything above that attracts surcharges. Failing the tests in a year makes surcharges payable for that year. Third-party sale has no ownership test, but attracts cross-subsidy surcharge.

Should we do rooftop solar or open access?

Rooftop first, in almost every case. Power from your own roof or land is used behind the meter, with no wheeling or transmission charges and no surcharges. Open access is for the demand left over once everything on site is used.

What happens to units our plant does not use when they arrive?

Depending on the state, surplus units can be banked with the DISCOM for use in a later slot, for a charge, or may lapse. Banking terms are one of the biggest differences between states.

Can one solar plant supply factories in different states?

Inter-state open access exists, but it can add central transmission charges (a waiver for solar is being phased out) and losses, and each state’s rules still apply at the receiving end. It needs a case-by-case calculation.

What should we look for in an open access power contract?

The term and tariff, the contracted capacity, shortfall and surplus units, payment security, and who carries the risk if a regulator revises a charge mid-term. These decide the saving as much as the headline tariff does.

Where do we find the rules for our state?

Our solar policy pages summarise each state’s charges and banking terms. Our engineers can then check your own state and tariff category against your bills.

Solar policy by state

Free feasibility study

Find out what open access would cost you

We model open access for your state and tariff category. An engineer replies within 48 hours.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study