Ginni Gopal – Boisar: 104 kWp metal sheet rooftop solar in Maharashtra
Generating since Jan 2023. Adhvanik Energy owns and runs it, and Ginni Gopal pays for each unit the plant generates, under a PPA.

- Capacity
- 104 kWp
- Installation
- Metal sheet roof
- Location
- Boisar, Maharashtra
- Finance model
- PPA / OPEX
This plant at a glance
- Client
- Ginni Gopal
- Capacity
- 104 kWp (DC), with 80 kW (AC) of inverters
- Service
- EPC + O&M
- Commissioned
- Jan 2023
- Status
- Operational. Owned and run by Adhvanik Energy.
Ginni Gopal – Boisar is a small plant by the standard of the list: 104 kWp, one roof or one block. Its 104 kWp of modules feed 80 kW of inverters, a DC/AC ratio of 1.30.
Since Jan 2023, the plant in Boisar has run through several monsoons. That history is the first thing an O&M review reads. Jan 2023 fell in the low-sun winter months.
Closest in capacity on the list: NDR Warehousing – Pune (100 kWp). In Maharashtra, in order of commissioning, Lemken – Nagpur comes before it and UCC – Pune, 166 kWp after.
More on the area: Maharashtra · Mumbai, Palghar, Boisar, Bhiwandi and Murbad. It is also listed in the filterable project list.
Engineering
What a metal sheet rooftop plant involves
Metal sheet is a light roof, and a 104 kWp array adds weight and wind load to purlins that were sized for the sheet alone. On a roof like this one in Boisar, a structural engineer confirms the roof can take the load, and the structure is designed for the wind speed under IS 875.
The layout in Boisar is drawn around ventilators and skylights, which keep their access and stay out of the modules' shade. A shed roof is often long and clear in one direction, which allows straight rows and short cable runs to the LT panel.
A plant in Boisar is only as good as its upkeep: inspections of connectors and inverters, cleaning that follows the local dust, and Asset Connect alerts on a string that has gone quiet.
Finance model
What PPA / OPEX means here
A PPA moves the capital cost to us. The client at Ginni Gopal – Boisar has had a solar supply since Jan 2023, with the cost arriving as a per-unit charge on what the plant supplies.
For the host site the PPA is a long contract, with terms from 5 to 25 years.
Boisar
Solar plants in Boisar
- Solar resource here
- 1,918 kWh/m² a yearAbout 1,603 kWh per kWp a year for a standard tilted system; July is the weakest month. Global Solar Atlas estimate for Boisar; a roof plant at roof tilt differs.
- Capacity range
- Under 250 kWp104 kWp here. 33 plants on our list are in this range.
- Type of installation
- Metal sheet roofThe most common factory roof.
- Finance option
- PPA / OPEXNo capital from the factory: it pays per unit generated.
The plant is the only Boisar plant on our list.
Boisar is covered on the page for Mumbai, Palghar, Boisar, Bhiwandi and Murbad, which lists 7 plants.
In Maharashtra the list shows 44 projects in 17 towns. Named sectors include electrical and electronics; agro; automotive; polymer.
Sector pages: industries we work with. Rules for Maharashtra: solar policy.
Projects
More plants near Boisar
Elsewhere in Maharashtra
- Exotic Fruits – Nashik1,332 kWp · Metal sheet roof · Jul 2026
- Baramati Cattlefeeds – Baramati771 kWp · Metal sheet roof · Jul 2026
- FUSO Glass – Murbad926 kWp · Metal sheet roof · Jul 2026
- Ozpure – Maharashtra867 kWp · Metal sheet roof · Jul 2026
Other plants on metal sheet roofs
- Lemken – Nagpur477 kWp · Metal sheet roof · Jul 2022
- Arihant Auto – Aurangabad162 kWp · Metal sheet roof · May 2022
- Legrand – Sinnar, 508 kWpMetal sheet roof · Apr 2022
- Soma Resort – Nashik, 50 kWpMetal sheet roof · Feb 2022
Common questions
What people ask about this plant
How big is the Ginni Gopal – Boisar plant?
Two figures describe the Ginni Gopal plant: 104 kWp on the module side and 80 kW (AC) on the inverter side. That is 30% more module capacity than inverter capacity (ratio 1.30), a normal design choice.
What roof is this Boisar plant built on?
Metal sheet, per the list. On a roof like that the mounting is chosen per roof, and sheet condition is checked before any module goes on.
Do you build plants in Maharashtra?
Yes. One plant is listed for Boisar, among 44 in Maharashtra. The free 7-day feasibility study needs only your town and a typical monthly bill.
Guides and glossary
Guides and terms behind a 104 kWp plant
- CAPEX or PPA: which solar model fits your factory?Read the guide
- Metal sheet, RCC, ground mount or carport: choosing the installationRead the guide
- Reading your electricity bill: the numbers that matter for solarRead the guide
Terms used on this page
Free feasibility study
Find out what your sheds can carry
A 104 kWp plant is one data point. The free 7-day study gives you the numbers for your own site.