Dabur – Rudrapur: 400 kWp rooftop solar on two roof types in Uttarakhand
Adhvanik Energy owns and runs it, and Dabur pays for each unit the plant generates, under a PPA. The plant has supplied the site since Nov 2023. It is one of 5 Dabur plants on our project list.
- Capacity
- 400 kWp
- Installation
- Metal sheet + RCC
- Location
- Rudrapur, Uttarakhand
- Finance model
- PPA / OPEX
This plant at a glance
- Client
- Dabur
- Industry
- FMCG
- Capacity
- 400 kWp (DC), with 310 kW (AC) of inverters
- Service
- EPC + O&M
- Commissioned
- Nov 2023
- Status
- Operational. Owned and run by Adhvanik Energy.
400 kWp is mid-sized for the list, enough to span a production hall or two. The array is 29% larger than the inverters, a DC/AC ratio of 1.29.
Since Nov 2023, the plant in Rudrapur has run through several monsoons. That history is the first thing an O&M review reads. Nov 2023 falls as the monsoon ends.
Closest in capacity on the list: Springtech Suspensions – Pithampur (400 kWp, Madhya Pradesh). Nov 2023 also saw HUL – Kandla (160 kWp, Gujarat) and Dabur – Rudrapur (1,000 kWp) commissioned. Of the Uttarakhand plants on our list, Dabur – Rudrapur, 1,000 kWp was commissioned just before it and Legrand – Haridwar just after.
Solar in the area: Uttarakhand. Find this plant in the full project list.
Engineering
What a rooftop on two roof types plant involves
Dabur – Rudrapur spans metal sheet and RCC roofs, so the plant is two engineering jobs under one design. The sheet roofs get clamp or adhesive mounting and wind-load checks. The concrete roofs get ballast or anchors and a waterproofing check.
Roof age differs too, so a block that needs re-sheeting or fresh waterproofing is dealt with before its share of the plant goes on.
Our standard O&M scope has 24 to 26 cleaning cycles a year, more where the dust and the monsoon in Rudrapur call for them, with AI-enabled checks on cleaning quality.
Finance model
What PPA / OPEX means here
Under a PPA the client buys electricity from a plant we own. The tariff per unit is set in the contract, and the client pays only for the units the plant generates.
Because we own the plant, we carry its performance: our O&M team runs it, and its output is what the contract is priced on. PPAs run 5 to 25 years.
Rudrapur
Rudrapur and the FMCG sector
- Solar resource here
- 1,781 kWh/m² a yearAbout 1,533 kWh per kWp a year for a standard tilted system; January is the weakest month. Global Solar Atlas estimate for Rudrapur; a roof plant at roof tilt differs.
- Capacity range
- 250 to 500 kWp400 kWp here. 36 plants on our list are in this range.
- Type of installation
- Metal sheet + RCCMetal sheet and RCC roofs, each with its own mounting.
- Finance option
- PPA / OPEXNo capital from the factory: it pays per unit generated.
We list 2 plants in Rudrapur, and Dabur – Rudrapur is one of them. The sector named there is FMCG.
In Uttarakhand the list shows 14 projects in 4 towns. Named sectors include FMCG; electrical and electronics; pharma; polymer.
FMCG sites tend to run packing and dispatch in daylight hours, which lines up with when a solar plant generates.
Warehouses and packing halls give long runs of clear roof, which keeps the array simple.
Sector page: FMCG solar. Rules for Uttarakhand: solar policy.
Projects
More plants near Rudrapur
Also in Rudrapur
- Dabur – Rudrapur, 1,000 kWpMetal sheet + RCC · Nov 2023
Elsewhere in Uttarakhand
- HUL – Haridwar, 332 kWpMetal sheet roof · Jul 2026
- Blink Infra – Selaqui332 kWp · Metal sheet roof · Dec 2025
- Plastiblends – Roorkee300 kWp · RCC · Apr 2024
Other FMCG plants
- Britannia – Bihta1,600 kWp · Metal sheet roof · Nov 2025
- Britannia – Hajipur1,050 kWp · Metal sheet roof · Oct 2025
- Dabur – Indore500 kWp · Metal sheet roof · Feb 2025
- Dabur – Newai480 kWp · Metal sheet + RCC + Ground mount · Mar 2024
Common questions
The Dabur – Rudrapur plant: questions and answers
When was the plant commissioned?
Our list records Nov 2023. That history is the first thing an O&M review reads.
Who maintains the Dabur plant?
We do. This Rudrapur plant is a PPA / OPEX plant, so Adhvanik Energy owns it, operates it and maintains it, and the host site pays per unit generated.
Can the Dabur – Rudrapur design be repeated at my site?
Only a check of your own site can say. The free 7-day feasibility study covers roof feasibility and the area available, a financial ROI sheet and a budgetary quote.
Guides and glossary
Guides and terms behind a 400 kWp plant
- CAPEX or PPA: which solar model fits your factory?Read the guide
- Metal sheet, RCC, ground mount or carport: choosing the installationRead the guide
- Behind-the-meter or net metering: which suits your site?Read the guide
Terms used on this page
Free feasibility study
Start with the numbers for your site
The free 7-day study gives a site in Rudrapur an ROI sheet, a policy check, roof feasibility and a budgetary quote. Expect an engineer within 48 hours.