Case study · FMCG

Solar on two roof types, with zero upfront cost

At Pantnagar (SIDCUL Rudrapur), Adhvanik Energy invested in, built and runs rooftop plants on two Dabur units under a long-term power purchase agreement.

Rooftop solar with a yellow walkway on a metal sheet roof at Dabur India, Silvassa

The challenge

Going green without tying up capital

Dabur wanted to go green and reduce the carbon intensity of its operations, but it wanted its capital free for expanding its core business. So it looked for a partner that would take on the capital and the operating burden of a solar plant, and still deliver cost savings and lower emissions.

Both Dabur units at Pantnagar combine metal sheet and RCC roofs, and each roof type has its own failure risk. Screw a structure through a metal sheet and every fixing is a possible leak, and a likely breach of the sheet maker’s warranty. Anchor into an RCC slab and you cut through the waterproofing that keeps the floor below dry.

The solution

How the plant was engineered

  • Adhesive mounting on metal sheet

    Rails are bonded to the sheet with adhesive instead of being screwed through it, for a roof with no fixings to seal.

  • Ballast on RCC

    On the slabs, the structure is held down by weight and not by anchors, and it is designed for the wind speed under IS 875, as applicable.

  • Safe access on both roofs

    Walkways and safety lines by design, so cleaning crews and engineers can reach every row safely.

  • Bifacial modules over the RCC

    Adhvanik used bifacial modules to capture extra light reflected off the RCC surface. An experimental white-paint coating on the RCC roof raised yields by 2–4%.

Implementation

How it was delivered

Adhvanik invested in, designed, built and commissioned the two Pantnagar plants, and operates them under the PPA.

Finance model

Adhvanik owns the plant (PPA)

Under the PPA, Adhvanik invests in the plants, owns them and runs them. Dabur makes no upfront investment and pays an agreed tariff for each unit the plants generate, set below its grid rate.

Because we own the plants, their performance is our responsibility. Our contracts carry a 95% uptime guarantee plus a performance-ratio guarantee.

Day to day, the plants report generation, performance ratio and alerts to Asset Connect. If something trips, our own O&M team responds remotely within 1 working day. If the fault cannot be fixed remotely, an engineer attends site within 2 working days.

Compare PPA with the other finance models

Results

Dabur India plants on our published list

From our commissioning records. Capacity is DC (kWp) unless marked AC.
PlantLocationRoof / configurationFinance modelCapacityCommissioned
Dabur – Rudrapur, 1,000 kWpRudrapur, UttarakhandMetal sheet + RCCPPA / OPEX1,000 kWpNov 2023
Dabur – Rudrapur, 400 kWpRudrapur, UttarakhandMetal sheet + RCCPPA / OPEX400 kWpNov 2023
Dabur – SilvassaSilvassa, Dadra and Nagar Haveli and Daman and DiuMetal sheet roofPPA / OPEX937 kWpApr 2026
Dabur – IndoreIndore, Madhya PradeshMetal sheet roofPPA / OPEX500 kWpFeb 2025
Dabur – NewaiNewai, RajasthanMetal sheet + RCC + Ground mountPPA / OPEX480 kWpMar 2024

Performance

Three years of operation, unit by unit

Unit 2 has 1,000 kW installed and Unit 3 has 400 kW, 1.4 MW across the two plants. Both were commissioned on 1 November 2023 and have completed three years of operation.

Performance ratio (PR) by financial year, from our monitoring records.
YearUnit 2 PRUnit 3 PR
2023–2483.7%80.8%
2024–2581.6%80.1%
2025–2681.4%77.5%
  • Grid outages cost generation

    Average grid-down time was 4% at Unit 2 and 9% at Unit 3, and the plants cannot generate while the grid is down. Adhvanik installed a DG sync on both plants to reduce the impact.

What happened next

More Dabur plants followed

Based on the plants’ performance, Dabur has awarded Adhvanik multiple projects. Alongside the two Pantnagar units, Dabur’s plants with us include Silvassa, Indore and Newai.

Photos

From the site

  • Solar plant: Dabur – Silvassa, Silvassa, Dadra and Nagar Haveli and Daman and DiuDabur – Silvassa, Silvassa, Dadra and Nagar Haveli and Daman and Diu

Does this match your site?

This approach fits if

  • You want solar savings without spending capital
  • Your site has more than one roof type
  • You’d rather the developer carries performance risk for the full term
  • You want one partner to build, own and maintain the plant

Related pages

Where to read next

Free feasibility study

Ask about a PPA for your roofs

The feasibility study is free, takes 7 days and carries no commitment. An engineer replies within 48 hours.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study