Dabur – Rudrapur: 1,000 kWp rooftop solar on two roof types in Uttarakhand

Generating since Nov 2023. Adhvanik Energy owns and runs it, and Dabur pays for each unit the plant generates, under a PPA. It is one of 5 Dabur plants on our project list.

Capacity
1,000 kWp
Installation
Metal sheet + RCC
Location
Rudrapur, Uttarakhand
Finance model
PPA / OPEX

Size, roof and finance model

Client
Dabur
Industry
FMCG
Capacity
1,000 kWp (DC), with 750 kW (AC) of inverters
Service
EPC + O&M
Commissioned
Nov 2023
Status
Operational. Owned and run by Adhvanik Energy.

At 1,000 kWp, a plant is generally built from blocks, each with its own inverter, so a fault stays local. Its 1,000 kWp of modules feed 750 kW of inverters, a DC/AC ratio of 1.33.

Commissioned in Nov 2023, the plant has several seasons of data. The question now is whether performance ratio has held steady. Nov 2023 came just after the monsoon, a clear-sky start.

For scale, the nearest match in capacity is Mitsubishi Electric – Pune (1,000 kWp, Maharashtra). HUL – Kandla (160 kWp, Gujarat) and Dabur – Rudrapur (400 kWp) were also commissioned in Nov 2023. Its nearest neighbour in Uttarakhand, in order of commissioning, is Dabur – Rudrapur, 400 kWp.

Engineering

How a 1,000 kWp plant is put together

The 1,000 kWp at the plant is split between roof types. Each block is designed on its own terms, and the blocks are then tied into one electrical design with a single metering and monitoring arrangement.

Walkways differ by block: fixed paths on the sheet roofs, where the sheet was not built for foot traffic, and marked routes between rows on the slabs.

After commissioning, Asset Connect logs output and alerts, and a monthly report an engineer signs sets measured performance ratio against the design.

Finance model

How the plant is paid for

The Dabur plant is a PPA / OPEX plant. Adhvanik Energy invested in it, owns it and runs it, and the client pays for each unit it generates at the tariff in its contract, with no capital of its own.

A PPA keeps the client's capital free for the factory itself; its cost is the tariff on the units the plant generates.

Rudrapur

Where Dabur – Rudrapur sits on our list

Solar resource here
1,781 kWh/m² a yearAbout 1,533 kWh per kWp a year for a standard tilted system; January is the weakest month. Global Solar Atlas estimate for Rudrapur; a roof plant at roof tilt differs.
Capacity range
1,000 kWp and above1,000 kWp here. 19 plants on our list are in this range.
Type of installation
Metal sheet + RCCMetal sheet and RCC roofs, each with its own mounting.
Finance option
PPA / OPEXNo capital from the factory: it pays per unit generated.

Rudrapur is a repeat location on the list, with 2 plants listed. Its one named sector is FMCG.

Across Uttarakhand our list holds 14 plants in 4 towns, commissioned between 2023 and 2026.

Consumer-goods lines such as filling, packing and conveying run through the day shift, so a roof plant produces when the load is already there.

The sizing question is how much the lines run on Sundays and shutdown days, because surplus on those days depends on the connection.

Projects

Other plants on the list

Also in Rudrapur

Elsewhere in Uttarakhand

Other FMCG plants

Common questions

Questions about Dabur – Rudrapur

How big is the Dabur – Rudrapur plant?

This Rudrapur plant has 1,000 kWp of modules (DC) feeding 750 kW of inverters (AC). Modules are quoted in kWp and inverters in kW. As a ratio that is 1.33: the array is rated above the inverters, which cap what the plant can feed the site at any moment.

What roof is the plant built on?

The plant spans metal sheet and RCC roofs, so each block follows its own checks: wind uplift and sheet condition on sheet, load and waterproofing on slabs.

Do you build plants in Uttarakhand?

Yes. 2 plants are listed for Rudrapur, among 14 in Uttarakhand. The free 7-day feasibility study needs only your town and a typical monthly bill.

Free feasibility study

Want a 1,000 kWp plant on your own site?

Tell us the roof type and last year's bills. An engineer gets back within 48 hours. The 7-day feasibility study costs nothing.

Call us+91 22 4618 3484Get a free feasibility study