Solar rules for factories in Uttarakhand

Uttarakhand caps net-metered solar at 1 MW. In July 2025 UERC refused to relax the ceiling for a factory that wanted to add 600 kW, and in August it rejected a 50 MW plant seeking net metering. The sections below give the rule, the reasoning and the routes left.

  • Rooftop regulationUERC Renewable Energy Regulations, 202312
  • Net metering ceiling1 MW123
  • Held in 2025UERC refused a 600 kW addition in July and rejected a 50 MW plant seeking net metering in August123
  • Green open accessUERC Green Energy Open Access Regulations, 2023; 100 kW or more, no limit for captive users4
Rules as of Nov 2026
Regulations and orders change. We quote rules and dates, not tariffs, surcharges or network-charge rates, because those are set by order and move. UERC regulates; UPCL is the distribution company; UREDA is the state renewable energy agency.

The 1 MW ceiling, and why it held

Net metering in Uttarakhand is governed by UERC’s Renewable Energy Regulations, 2023, which set a ceiling of 1 MW.12 Two 2025 decisions show the commission holding it.

As reported by Mercom and SolarQuarter. The orders themselves are on the UERC website.
WhenWhat UERC decided
July 2025A factory in Dehradun with 1 MW already installed (part owned, part under a RESCO) asked to add 600 kW under net metering, which would have taken it to 1.6 MW. UERC refused, calling relaxation neither justified nor prudent.12
July 2025UERC found that two net-metering arrangements under one connection were not technically or regulatorily feasible, and said MNRE guidelines allow net metering, net billing or gross metering and do not require net metering. The petitioner had also cited the state’s Solar Policy 2023 against the cap; UERC kept the 1 MW ceiling. UPCL opposed relaxation.2
August 2025A Van Panchayat sought net metering for a 50 MW plant on government land. UERC said net metering is allowed only for rooftop and small solar plants of up to 1 MW.3

UREDA supported the 600 kW addition and pointed to earlier 2 MW approvals at two defence campuses. UERC distinguished those as a different model, approved with a no-objection certificate, where surplus power is injected free of cost rather than compensated as under net metering.2 That is the one route above 1 MW the commission has acknowledged.

Green energy open access, notified in 2023

UERC’s Green Energy Open Access Regulations, 2023 set the eligibility test at 100 kW or more of contracted demand or sanctioned load. There is no load limit for captive consumers or for renewable energy generators.4 Press coverage dates the regulations to late 2023; the commission’s own statement of reasons carries the notification date.

The central rules say the same on threshold and captive users.56 For charges and banking, use the schedule UERC publishes for your distribution company, because those figures are set by order.

Planning for roof space above 1 MW

A factory with roof space for more than 1 MW cannot net-meter all of it. Two net-metering arrangements under one connection were found not feasible, so adding a second plant later does not get round the ceiling.2 The roof beyond 1 MW needs a different arrangement, such as behind-the-meter self-consumption, a no-objection-certificate route if UPCL and UERC allow it for your site, or open access.

UERC’s remark that MNRE guidelines do not require net metering matters for design: net billing and gross metering are also named in those guidelines, so ask UPCL which of them it accepts at your connection.2

For a factory in the Haridwar, Rudrapur or Roorkee clusters with contracted demand above 100 kW, green energy open access is a further route for the load that rooftop cannot cover.4

Confirm with UPCL or UREDA

Questions to put to the distribution company in writing before you finalise the design:

  1. Whether a second rooftop plant at the same premises or connection counts against the same 1 MW.
  2. Which of net metering, net billing, gross metering or behind-the-meter UPCL will accept for capacity beyond 1 MW.
  3. Whether a no-objection-certificate arrangement, with surplus injected free of cost, is available for your site.
  4. The registration steps with UREDA for your project.
  5. For open access: the charges and banking terms in force for your distribution company this financial year.

Sources

Checked 4 Nov 2026. Where a source is trade press, the regulator’s own order or regulation text is the authority; confirm the version in force for your connection.

  1. Mercom: UERC rejects plea to relax 1 MW rooftop solar cap for net metering (July 2025) (opens in a new tab)
  2. SolarQuarter: Uttarakhand regulator denies request to exceed 1 MW rooftop solar net metering limit (July 2025) (opens in a new tab)
  3. SolarQuarter: UERC rejects 50 MW solar power proposal over net metering constraints (August 2025) (opens in a new tab)
  4. Power Line: UERC notifies Green Energy Open Access Regulations, 2023 (opens in a new tab)
  5. Mercom: consumers with aggregate demand of 100 kW can avail green energy open access (opens in a new tab)
  6. Mercom: no load limit for green energy open access for captive consumers (June 2022) (opens in a new tab)

Common questions

Questions on the Uttarakhand 1 MW ceiling

Speak with an industrial solar engineer
What is the net-metering limit for a factory in Uttarakhand?

UERC’s Renewable Energy Regulations, 2023 set a ceiling of 1 MW under net metering. UERC declined to relax it in July 2025 and rejected a 50 MW plant seeking net metering in August 2025.

Does the Uttarakhand solar policy raise the 1 MW limit?

In 2025 a petitioner cited the state Solar Policy 2023 against the cap, and UERC kept the 1 MW ceiling.

Who can use green energy open access in Uttarakhand?

Consumers with a contracted demand or sanctioned load of 100 kW or more. Captive consumers and renewable energy generators face no load limit.

Keep reading

Guides, glossary terms and the other seven states

Free feasibility study

More than 1 MW of roof in Uttarakhand? Send us your bill

Send us your bill and sanctioned load. An engineer replies within 48 hours and the study includes the metering route that fits your connection.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study