How it works
The inverters feed your main LT (low-tension) panel or an HT (high-tension) bus inside the factory. Whenever the sun is up, the factory draws on solar first and the grid supplies only what solar cannot cover. Because the power stays inside your premises, there are no wheeling charges, open-access surcharges or transmission losses, and every unit replaces one you would have bought at your energy charge. A few states levy network or grid-support charges on rooftop generation, so check yours. A net-metered plant also sits behind the meter: it serves your load first and exports only the surplus.
Sizing to your daytime load
A behind-the-meter plant is sized to the load it will meet, and the roof sets only the upper limit. The key data is your daytime consumption on working days and on weekly offs. A plant sized to the weekday base load is absorbed almost entirely on site, so surplus is avoided by design; on Sundays and holidays the little that remains is held back or, where your state allows it, credited.
When export is not allowed
Where net metering is not available at your size, or not worth having, the plant is fitted with an export-limiting (zero-export) controller. It trims the inverters' output whenever the plant would otherwise push power into the grid. Even a zero-export plant is connected to the grid, so check your state's approval process for it.
Illustrative example
Worked example: fitting a plant to a load
A two-shift factory working six days a week.
- Daytime load, Monday to Saturday
- 600–900 kW
- Daytime load on Sunday
- 150 kW
- Plant designed for
- The weekday load, so almost every weekday unit is used on site
- On Sundays
- The surplus is held back by a zero-export controller (or credited where your state allows net metering or net billing at this size)
Illustrative load figures. Your study uses your own meter data.
What to gather before sizing
- Twelve months of bills, plus 15-minute or hourly load data if your meter records it
- Your shift pattern, weekly offs and annual shutdown weeks
- Planned expansions that will add daytime load
- Your state's net-metering terms, to value any surplus