How net metering works
Your plant feeds your factory first. When it produces more than the factory is using, on a Sunday or a holiday, the surplus flows out through a bidirectional meter and is recorded as export. At the end of the billing period, exported units are set off against the units you imported, and you pay for the difference. Surplus credit left at the end of the settlement period is handled as your state's regulations say, often at a rate well below your tariff.
Who can use it
The Electricity (Rights of Consumers) Amendment Rules, 2021 let state commissions allow net metering for loads up to 500 kW or the sanctioned load, whichever is lower. Above 500 kW, the central rule points loads to gross metering (or net billing); states set the arrangement. Each state sets its own limits and terms in its regulations; Rajasthan, for instance, moved to the 500 kW limit in September 2021. Rules as of Nov 2026.
Why net metering matters less to many factories
A factory running two or three shifts, six days a week, uses almost every unit its rooftop plant generates. Net metering earns its keep on weekly offs, holidays and shutdowns, when surplus would otherwise be wasted. Because states revise their net-metering rules from time to time, we treat export credits as a bonus and size the plant so the economics stand on self-consumption. Behind-the-meter solar explains how that sizing works.
Illustrative example
Worked example: one month's bill
A factory with a net-metered rooftop plant.
- Plant generation
- 60,000 kWh
- Used directly by the factory
- 52,000 kWh
- Exported on Sundays and holidays
- 8,000 kWh
- Imported from the grid at other times
- 1,00,000 kWh
Units billed: 1,00,000 − 8,000 = 92,000 kWh.
Illustrative numbers. How exports are valued, and over what period, depends on your state.
What to confirm for your site
- Your state's net-metering limit for industrial consumers, and how it relates to your sanctioned load
- The settlement period, and what happens to surplus credit at the end of it
- Whether exports and imports are netted within time-of-day slots
- Any charges your state applies to net-metered industrial consumers
- Meter replacement, testing and the approval timeline
Net metering on our plants and in the study
On metal sheet roofs, plants can be net-metered or behind-the-meter. Every feasibility study includes a policy check for your state and connection.