Solar policy · HERC

Solar rules for factories in Haryana

In Haryana, 500 kW is the line that decides your metering. A September 2026 HERC order sent a 1,412 kW university rooftop to gross metering instead. The sections below cover what that means and how open access has changed.

  • Net metering ceiling500 kW; HERC refused to relax it in Sept 20261
  • Above the ceilingGross metering: you export all output and are paid a HERC-determined tariff1
  • Green open accessHERC Green Energy Open Access Regulations, 2023, amended; approved 25 Feb 202523
  • Reliability chargesHERC said in April 2023 it would not levy them4
Rules as of Nov 2026
Regulations and orders change. We quote rules and dates, not tariffs, surcharges or network-charge rates, because those are set by order and move. HERC regulates; DHBVN and UHBVN are the distribution companies; HAREDA is the state renewable energy agency.

The 500 kW line and gross metering

Haryana’s rooftop rules sit in HERC’s Rooftop Solar Grid Interactive Systems Based on Net Metering Regulations, 2019. The net-metering ceiling in practice is 500 kW, which the distribution company links to the Electricity (Rights of Consumers) Rules, 2020.1

The September 2026 order
On 21 September 2026 HERC refused to relax the ceiling for a 1,412 kW rooftop project at a state university in Palwal. The university had a 5,000 kW load sanction, but HERC held that a load sanction does not create a vested right to net metering, especially where the project had no technical feasibility approval or letter of approval under the 2019 regulations. It directed the university to apply under the gross-metering framework instead.1
As reported by SolarQuarter, 22 September 2026.
Under gross meteringWhat HERC directed
GenerationThe full 1,412 kW output is injected into the grid and paid at a tariff HERC determines.1
ConsumptionBilled separately at prevailing retail tariffs.1
TimelineThe distribution company must sign interconnection agreements, install automated meter reading and synchronise within 45 days of the application.1

HERC issued a draft second amendment to the rooftop regulations in mid-2025, covering energy accounting and surplus power compensation, and passed a final order on it on 30 October 2025. HERC dismissed a review petition against that order on 22 September 2026.67 We have not seen what the final text changed, so ask HERC or your distribution company for the consolidated regulations before you model surplus power. The 500 kW ceiling was still cited as in force in September 2026.1

Green energy open access: amended in 2025, tested in 2026

HERC’s Green Energy Open Access Regulations date from April 2023, and an amendment was approved on 25 February 2025. After the amendment, a consumer with a sanctioned load of 100 kW or more, through a single connection or several in the same electricity division, is eligible.23

In April 2023, in the order approving the regulations, HERC said it would not levy reliability charges and that no charges beyond those in the regulations would apply to green energy open access consumers.4

In October 2026 HERC decided a petition by a steel maker with units in Sonipat that draws on a 9 MW captive solar plant in Rewari. Its units share feeders with consumers who do not want open access, and the procedure generally asks consumers on an independent feeder to apply collectively. HERC held that an eligible consumer cannot be refused green energy open access only because its feeder neighbours decline a collective application, provided it accepts the system constraints and power-cut limits that apply.5

Design around the 500 kW line

In Haryana, 500 kW is the design line. A plant at or below it can use net metering and offset your retail tariff unit for unit. A plant above it goes to gross metering, where you are paid a regulator-determined tariff for all generation and still buy your consumption at retail. The economics are different, so the feasibility study has to price both.1

Do not size a larger plant on the strength of your load sanction. HERC said in September 2026 that sanctioned load alone gives no right to net metering, and that approvals should be in place before you invest.1

For a Gurugram, Manesar or Bahadurgarh factory with a big load and limited roof, open access for the remainder is worth pricing, and HERC’s October 2026 order shows a shared feeder need not block it.5

Confirm with DHBVN or UHBVN

Questions to put to the distribution company in writing before you finalise the design:

  1. Technical feasibility approval and letter of approval for your project before you buy equipment.
  2. What the final order of 30 October 2025 on the second amendment to the rooftop regulations changed for energy accounting and surplus power.
  3. The gross-metering tariff HERC has determined for the year of your commissioning.
  4. Whether your feeder is independent or shared, if you are considering open access.
  5. The distribution company’s current wheeling and banking terms for green open access.

Sources

Checked 4 Nov 2026. Where a source is trade press, the regulator’s own order or regulation text is the authority; confirm the version in force for your connection.

  1. SolarQuarter: HERC rejects 1,412 kW net metering relaxation, orders gross metering for a university solar project in Haryana (September 2026) (opens in a new tab)
  2. Renewable Watch: HERC notifies Green Open Access Regulations (April 2023) (opens in a new tab)
  3. SolarQuarter: HERC amends green energy open access rules, 2025 (opens in a new tab)
  4. Saur Energy: HERC approves green energy open access rules, ensures no reliability charges (April 2023) (opens in a new tab)
  5. SolarQuarter: HERC allows individual consumers green energy open access without collective applications (October 2026) (opens in a new tab)
  6. SolarQuarter: HERC dismisses rooftop solar review petition against its 30 October 2025 order (September 2026) (opens in a new tab)
  7. Mercom: Haryana issues draft amendment to rooftop solar rules (2025) (opens in a new tab)

Common questions

Questions on the Haryana 500 kW line

Speak with an industrial solar engineer
What is the net-metering limit for a factory in Haryana?

The ceiling in practice is 500 kW. In September 2026 HERC refused to relax it for a 1,412 kW rooftop project and directed the consumer to the gross-metering route.

What is gross metering in Haryana?

All generation is injected into the grid and paid at a tariff HERC determines, while your consumption is billed separately at retail tariffs.

Can a factory on a shared feeder get green open access in Haryana?

In October 2026 HERC held that an eligible consumer cannot be denied green energy open access only because other consumers on its independent feeder decline a collective application, if it accepts the system constraints.

Keep reading

Guides, glossary terms and the other seven states

Free feasibility study

Above or below 500 kW? We will price both routes

Send us your bill and sanctioned load. An engineer replies within 48 hours and the study includes the metering route that fits your connection.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study