Rooftop: four metering routes
The rooftop rules sit in the MPERC (Grid Interactive Renewable Energy Systems and Related Matters) Regulations. Reports cite them as 2023, while the 2026 amendment papers call them Revision-II of 2024, so check the official title in the gazette. They cover net metering, gross metering, group net metering and virtual net metering, and the distribution companies must allow them without discrimination, first come first served. A consumer with pending arrears to the distribution company is not entitled to any of them.1
The report we relied on gives capacity limits of 500 kW to 1 MW depending on the arrangement. The regulation text sets which limit applies to which route, so take the number for your connection from the text rather than from a summary.1 Group net metering is permitted, but wheeling charges and other surcharges apply to the beneficiary connections.1
A first amendment was drafted on 15 May 2026. It would exempt PM Surya Ghar applicants from processing fees, fold the connection agreement into the online application, rename the group net metering agreement as a virtual net metering agreement, and count prosumer generation toward the distribution companies’ renewable purchase obligations. It is reported as issued in June 2026; confirm that in the gazette.56
| Question | What the reported rules say |
|---|---|
| Which routes exist? | Net metering, gross metering, group net metering, virtual net metering.1 |
| Who is shut out? | Consumers with pending arrears to the distribution company.1 |
| Does group net metering avoid charges? | No. Wheeling charges and other surcharges apply to beneficiary connections.1 |
| Can net or gross metering run with open access? | No. Consumers on net or gross metering are not eligible for open access under the regulations.1 |
Green open access and the additional surcharge
MPERC’s 2023 regulations on the methodology for open access and banking charges for green energy consumers, as amended in 2024, govern those charges.2 Under the second amendment, no additional surcharge is levied on a green energy open access consumer drawing power up to its contract demand, as long as the consumer pays fixed charges to the distribution company.2
The central rules set 100 kW or more as the eligibility test, with no load limit for captive users.34 Confirm the threshold and the banking terms in MPERC’s current text.
Pick a primary route
In Madhya Pradesh you pick a primary route. If your roof can carry most of your daytime load, rooftop on net or gross metering keeps things simple. If your load is large and the roof is not, open access with an offsite plant is the route, and rooftop net metering would take you out of it, as reported.1
Fixed charges matter twice. They are the condition for the additional-surcharge exemption on open access, and they stay on your bill however much solar you generate.2 Ask your distribution company how fixed charges are billed on your connection before you model savings.
If you operate several sites, test group net metering against its wheeling charges, because the reported rules include no wheeling exemption for it.1
Confirm with your regional distribution company
Questions to put to the distribution company in writing before you finalise the design:
- The capacity limit that applies to your arrangement in the 2023 regulation text.
- Whether you have any pending arrears, because they bar access to every rooftop route.
- In writing: that choosing net or gross metering will not block an open access application you may want later.
- How fixed charges are billed, and whether you meet the condition for the additional-surcharge exemption.
- The wheeling charges that would apply to group net metering between your sites.
Sources
Checked 4 Nov 2026. Where a source is trade press, the regulator’s own order or regulation text is the authority; confirm the version in force for your connection.
- Energetica India: MPERC introduces new regulations for renewable energy systems (April 2024) (opens in a new tab)
- OmniCore: MPERC methodology for determination of open access and banking charges for green energy open access consumers, Second Amendment (June 2024) (opens in a new tab)
- Mercom: consumers with aggregate demand of 100 kW can avail green energy open access (opens in a new tab)
- Mercom: no load limit for green energy open access for captive consumers (June 2022) (opens in a new tab)
- SolarQuarter: MPERC draft amendment eases rooftop solar adoption under PM Surya Ghar (May 2026) (opens in a new tab)
- TeamLease RegTech: MPERC Grid Interactive Renewable Energy Systems and Related Matters Regulations, first amendment, 2026 (opens in a new tab)