Solar policy · TNERC

Solar rules for factories in Tamil Nadu

In Tamil Nadu the rooftop question is one levy: network charges on solar generation. It has been cut, challenged and stayed. The sections below give the timeline, the 2025 open access regulations and what to ask before you sign.

  • Rooftop levyPer-unit network charges from the 2021 tariff order; contested in the Madras High Court123
  • MSME reliefNetwork charges on rooftop solar cut by 50% in Dec 20234
  • Green open accessTNERC regulations of 18 Sep 2025; HT and EHT consumers from 63 kVA5
  • Captive plantsAutomatic right to open access under the 2025 regulations5
Rules as of Nov 2026
Regulations and orders change. We quote rules and dates, not tariffs, surcharges or network-charge rates, because those are set by order and move. TNERC regulates; TNPDCL is the distribution company.

Network charges: the open question

TNERC’s generic tariff order of 2021 introduced per-unit network charges on rooftop solar generation. The rate depends on consumer voltage and has been revised since. We do not quote it, because the position is in litigation and a stale figure would mislead.12

Dates and outcomes as reported by the sources listed below. Court orders bind the parties to them.
WhenWhat happened
2021TNERC’s generic tariff order sets network charges on rooftop solar generation.1
Dec 2023The state halves the network charge for MSME rooftop solar consumers.4
22 Dec 2024In South India Spinners Association v. TNPDCL (W.P. No. 22200 of 2022, a batch of petitions decided by Justice Anita Sumanth), the Madras High Court holds that separate network charges cannot be levied because they were already embedded in the tariff, and bars the charge for the association’s members.36
2025Trade press reports a Madras High Court judgment striking down the charges on industrial captive rooftop plants.2 A division bench interim stay is reported in a separate matter involving a Coimbatore textile mill, and industry groups fear the utility could use it to resume collection from everyone.1
Nov 2026We found no later judgment. Confirm the position that applies to your connection with TNPDCL.

Sources disagree on the scope of the 2025 rulings: some describe a general quashing and others an order limited to named petitioners. That is the reason to treat your own connection as the unit of analysis.

Green energy open access, 2025 regulations

TNERC notified its Terms and Conditions for Green Energy Open Access Regulations, 2025 on 18 September 2025 (Notification No. TNERC/GEOA/25-1/2025). Eligibility is stated as EHT and HT consumers with a contracted demand of at least 63 kVA, a test the state sets separately from the 100 kW test in the central rules. Captive generating plants have an automatic right to open access.5

The charges are the familiar set: transmission and wheeling, cross-subsidy surcharge, additional surcharge, standby charges capped at 125% of the applicable tariff, banking charges settled in kind, and deviation settlement. Concessions apply only to transactions inside the state, not to inter-state or exchange purchases. Surplus power can be adjusted within the billing cycle.5

Run the numbers with and without the charge

If you buy a plant (CAPEX), the network charge lands on your bill, so run the financial model both ways: with the charge and without it. If you sign a PPA, ask who bears the charge if it is reinstated, and whether the tariff moves with it.

An MSME should confirm its classification, because the 50% reduction depends on it.4 An HT consumer with 63 kVA or more of contracted demand has a second route in the 2025 open access regulations, which is worth pricing next to rooftop.

Do not rely on a court headline from another consumer’s case. Ask your distribution company whether it is billing network charges on rooftop plants like yours today, and get that in writing.

Confirm with TNPDCL

Questions to put to the distribution company in writing before you finalise the design:

  1. Whether network charges are being billed on rooftop plants at your voltage level today, and at what rate.
  2. Whether you are covered by the December 2024 order or another petition, for example through an association you belong to.
  3. Your MSME classification and whether the 50% reduction applies.
  4. For a PPA: who bears network charges if they return, and how the tariff adjusts.
  5. For open access: whether your contracted demand meets the 63 kVA test, and the current charges for your category.

Sources

Checked 4 Nov 2026. Where a source is trade press, the regulator’s own order or regulation text is the authority; confirm the version in force for your connection.

  1. Energetica India: Madras HC grants stay on cancellation of rooftop solar network charges for industries (May 2025) (opens in a new tab)
  2. Energetica India: Madras High Court strikes down network charges on rooftop solar projects for captive use (opens in a new tab)
  3. Taxscan: Madras HC rules no separate network charges, already included in tariff (opens in a new tab)
  4. Mercom: Tamil Nadu cuts rooftop solar network charges for MSMEs (Dec 2023) (opens in a new tab)
  5. SolarQuarter: TNERC issues new regulations for green energy open access, 2025 (opens in a new tab)
  6. TaxGuru: Madras High Court on network charges for energy produced by rooftop solar generators (W.P. No. 22200 of 2022) (opens in a new tab)

Common questions

Questions on Tamil Nadu network charges

Speak with an industrial solar engineer
Does a factory pay network charges on rooftop solar in Tamil Nadu?

TNERC’s 2021 tariff order introduced them, and they have been challenged in the Madras High Court since 2024. Reports describe orders for some petitioners and a stay in a separate case, so confirm the position for your connection with TNPDCL.

What did Tamil Nadu change for MSMEs in December 2023?

It halved the network charge on rooftop solar for MSME consumers.

Who can use green energy open access in Tamil Nadu?

Under the 2025 regulations, EHT and HT consumers with a contracted demand of at least 63 kVA, and captive generating plants, which have an automatic right.

Keep reading

Guides, glossary terms and the other seven states

Free feasibility study

Model your Tamil Nadu plant with and without network charges

Send us your bill and sanctioned load. An engineer replies within 48 hours and the study includes the metering route that fits your connection.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study