The net metering cap and the behind-the-meter directions
APERC Regulation No. 4 of 2023 governs grid-interactive rooftop solar under net and gross metering. It limits net metering to rooftop systems of up to 500 kWp for projects approved after it took effect. Older systems keep their terms: those commissioned before the regulation, and those under construction with approved feasibility, stay under the rules in force when they were approved, and systems of 500 to 1,000 kWp need not change their metering arrangements or contract terms.1
A draft amendment would add virtual and group net metering and a role for distributed energy aggregators. We could not confirm that it has been finalised.4
| Question | APERC’s directions, August 2026 |
|---|---|
| Is permission needed? | No prior permission or feasibility approval. Prior intimation is mandatory, with capacity and single-line diagrams.2 |
| Cross-subsidy and additional surcharge? | Not applicable to behind-the-meter rooftop plants, including third-party investment and external financing models.2 |
| What still applies? | Regulated capacity charges set by the commission.2 |
| What is the penalty for connecting without notice? | Penal action under Sections 142 and 146 of the Electricity Act, 2003.2 |
Green energy open access, 2024
APERC notified its Green Energy Open Access, Charges and Banking Regulation, 2024 in May 2024. It provides banking for consumers using green energy open access, subject to conditions.3
The central rules put the eligibility test at 100 kW or more and remove load limits for captive users.56 Confirm the threshold and the current charges in APERC’s text before you plan around open access.
Size to your daytime load, behind the meter
In Andhra Pradesh the clean route for a factory is a plant sized to your own daytime load and connected behind the meter. The August 2026 directions remove the permission step and the open-access surcharges for that design, and they extend to third-party financing, which matters if you are weighing a PPA against buying the plant.2
If you want to export or to net-meter more than 500 kWp, the 2023 regulation caps you, and older approvals are grandfathered only for plants that already had them.1
The directions leave regulated capacity charges in place, so check whether any apply to your connection when you compare savings.2
Confirm before you design behind the meter
Questions to put to the distribution company in writing before you finalise the design:
- That your plant is designed as behind the meter, with no injection into the main grid at any time, including during synchronisation.
- The prior intimation format, and the capacity and single-line diagram details the company needs.
- Whether any regulated capacity charges apply to your connection.
- If you want net metering: that the project was approved under the 2023 regulation and the 500 kWp cap applies.
- Whether the draft amendment on virtual and group net metering has been notified.
Sources
Checked 4 Nov 2026. Where a source is trade press, the regulator’s own order or regulation text is the authority; confirm the version in force for your connection.
- SolarQuarter: APERC clarifies net metering continuity for existing rooftop projects above 500 kWp (June 2026) (opens in a new tab)
- SolarQuarter: APERC simplifies behind-the-meter rooftop solar regulations and removes surcharge burden (August 2026) (opens in a new tab)
- India Environment Portal: APERC Green Energy Open Access, Charges and Banking Regulation, 2024 (opens in a new tab)
- Energetica India: APERC draft amendment aims to strengthen rooftop solar with net metering reforms (opens in a new tab)
- Mercom: consumers with aggregate demand of 100 kW can avail green energy open access (opens in a new tab)
- Mercom: no load limit for green energy open access for captive consumers (June 2022) (opens in a new tab)