Solar policy · APERC

Solar rules for factories in Andhra Pradesh

Andhra Pradesh caps new net-metered rooftop plants at 500 kWp, but in August 2026 APERC said behind-the-meter plants need no discom permission and pay no open-access surcharges. That second rule is the one for factories.

  • Net metering ceiling500 kWp for projects approved after APERC Regulation 4 of 20231
  • Older plantsSystems of 500 to 1,000 kWp already approved keep their agreements1
  • Behind the meterNo prior permission; cross-subsidy and additional surcharge do not apply (Aug 2026)2
  • Green open accessAPERC Green Energy Open Access, Charges and Banking Regulation, 20243
Rules as of Nov 2026
Regulations and orders change. We quote rules and dates, not tariffs, surcharges or network-charge rates, because those are set by order and move. APERC regulates the distribution companies and sets the rooftop and open access terms.

The net metering cap and the behind-the-meter directions

APERC Regulation No. 4 of 2023 governs grid-interactive rooftop solar under net and gross metering. It limits net metering to rooftop systems of up to 500 kWp for projects approved after it took effect. Older systems keep their terms: those commissioned before the regulation, and those under construction with approved feasibility, stay under the rules in force when they were approved, and systems of 500 to 1,000 kWp need not change their metering arrangements or contract terms.1

A draft amendment would add virtual and group net metering and a role for distributed energy aggregators. We could not confirm that it has been finalised.4

The behind-the-meter directions
In August 2026 APERC issued practice directions for behind-the-meter rooftop plants used for captive consumption. They connect to the consumer’s internal bus bars without prior permission, feasibility approval or line clearance from the distribution company. Prior intimation is mandatory before interconnection or islanding, and nothing may be injected into the main grid during synchronisation.2
As reported by SolarQuarter, 19 August 2026. Read the practice directions for the full conditions.
QuestionAPERC’s directions, August 2026
Is permission needed?No prior permission or feasibility approval. Prior intimation is mandatory, with capacity and single-line diagrams.2
Cross-subsidy and additional surcharge?Not applicable to behind-the-meter rooftop plants, including third-party investment and external financing models.2
What still applies?Regulated capacity charges set by the commission.2
What is the penalty for connecting without notice?Penal action under Sections 142 and 146 of the Electricity Act, 2003.2

Green energy open access, 2024

APERC notified its Green Energy Open Access, Charges and Banking Regulation, 2024 in May 2024. It provides banking for consumers using green energy open access, subject to conditions.3

The central rules put the eligibility test at 100 kW or more and remove load limits for captive users.56 Confirm the threshold and the current charges in APERC’s text before you plan around open access.

Size to your daytime load, behind the meter

In Andhra Pradesh the clean route for a factory is a plant sized to your own daytime load and connected behind the meter. The August 2026 directions remove the permission step and the open-access surcharges for that design, and they extend to third-party financing, which matters if you are weighing a PPA against buying the plant.2

If you want to export or to net-meter more than 500 kWp, the 2023 regulation caps you, and older approvals are grandfathered only for plants that already had them.1

The directions leave regulated capacity charges in place, so check whether any apply to your connection when you compare savings.2

Confirm before you design behind the meter

Questions to put to the distribution company in writing before you finalise the design:

  1. That your plant is designed as behind the meter, with no injection into the main grid at any time, including during synchronisation.
  2. The prior intimation format, and the capacity and single-line diagram details the company needs.
  3. Whether any regulated capacity charges apply to your connection.
  4. If you want net metering: that the project was approved under the 2023 regulation and the 500 kWp cap applies.
  5. Whether the draft amendment on virtual and group net metering has been notified.

Sources

Checked 4 Nov 2026. Where a source is trade press, the regulator’s own order or regulation text is the authority; confirm the version in force for your connection.

  1. SolarQuarter: APERC clarifies net metering continuity for existing rooftop projects above 500 kWp (June 2026) (opens in a new tab)
  2. SolarQuarter: APERC simplifies behind-the-meter rooftop solar regulations and removes surcharge burden (August 2026) (opens in a new tab)
  3. India Environment Portal: APERC Green Energy Open Access, Charges and Banking Regulation, 2024 (opens in a new tab)
  4. Energetica India: APERC draft amendment aims to strengthen rooftop solar with net metering reforms (opens in a new tab)
  5. Mercom: consumers with aggregate demand of 100 kW can avail green energy open access (opens in a new tab)
  6. Mercom: no load limit for green energy open access for captive consumers (June 2022) (opens in a new tab)

Common questions

Questions on Andhra Pradesh behind-the-meter plants

Speak with an industrial solar engineer
What is the net-metering limit in Andhra Pradesh?

APERC Regulation No. 4 of 2023 limits net metering to rooftop systems of up to 500 kWp for projects approved after it took effect. Systems approved earlier keep their existing terms.

Do behind-the-meter rooftop plants pay open-access surcharges in Andhra Pradesh?

No. APERC’s August 2026 practice directions say cross-subsidy surcharge and additional surcharge do not apply to behind-the-meter rooftop plants, including third-party and externally financed models. Regulated capacity charges still apply.

Do I need discom approval for a behind-the-meter plant in Andhra Pradesh?

No prior permission or feasibility approval is needed, but prior intimation is mandatory and nothing may be injected into the main grid.

Keep reading

Guides, glossary terms and the other seven states

Free feasibility study

Sizing a behind-the-meter plant in Andhra Pradesh? Send us your bill

Send us your bill and sanctioned load. An engineer replies within 48 hours and the study includes the metering route that fits your connection.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study