Grid & policy

Cross-subsidy surcharge (CSS)

Cross-subsidy surcharge (CSS) is a per-unit charge that open-access consumers pay their DISCOM to make up for the cross-subsidy their regular tariff would have carried to keep other consumers' tariffs low.

Why open-access buyers pay it

Industrial and commercial tariffs in India are set above the cost of supply, so that tariffs for farms and homes can be kept lower. When a factory buys its power elsewhere through open access, the DISCOM (distribution company) loses that contribution. The cross-subsidy surcharge recovers it on each unit the factory takes through open access.

How the surcharge is calculated

The Tariff Policy, 2016 gives the formula: S = T − [C / (1 − L/100) + D + R], where S is the surcharge, T the tariff payable by your consumer category, C the DISCOM's per-unit cost of power purchase, L the aggregate system losses (in %) at your voltage level, D the per-unit wheeling charge at that voltage, and R the per-unit cost of carrying regulatory assets. The same policy caps the surcharge at 20% of the tariff applicable to the consumer category. Each state commission works out its own figure in its tariff orders.

Who does not pay it

  • Captive and group captive users whose plant meets the 26% ownership and 51% consumption tests: the Electricity Act exempts them.
  • Rooftop and other behind-the-meter plants: the power never travels over the DISCOM's network, so it is not open access.

For green open access, the 2022 rules also cap any increase in the surcharge at 50% over the 12 years from the start of open access. Rules as of Nov 2026.

Illustrative example

Worked example: what the surcharge can cost

A third-party open-access buyer taking 50 lakh units a year.

Grid tariff for the category
₹8.00 per kWh
Maximum surcharge at 20% of tariff
₹1.60 per kWh
Annual surcharge at that ceiling
50 lakh × ₹1.60 = ₹80 lakh

Under a qualifying group captive structure, the same power carries no cross-subsidy surcharge.

Illustrative numbers. Your state's actual surcharge is published in its latest tariff order.

What to check in an open-access proposal

  • The surcharge used in the proposal, and which tariff order it comes from
  • Whether the proposal assumes captive status, and who carries the risk if the plant fails verification
  • How the surcharge is escalated over the contract term
  • Whether the green open access cap on increases applies to you

Where group captive removes the surcharge

We build offsite solar wheeled to your plant, for loads larger than your roof can serve. Where the group captive tests can be met, that power carries no cross-subsidy surcharge.

See open access solar

Sources

  1. KSERC: cross-subsidy surcharge formula under the revised Tariff Policy of 28 January 2016 (opens in a new tab)
  2. Tariff Policy 2016 proviso capping the surcharge at 20% of tariff, as quoted in an APERC order (opens in a new tab)
  3. JMK Research: Green Energy Open Access Rules 2022, summary of provisions (opens in a new tab)
  4. Power Line: Electricity (Amendment) Rules, 2026 and captive users (opens in a new tab)

Related terms

  • Grid & policy

    Additional surcharge

    A per-unit charge under Section 42(4) of the Electricity Act that lets a DISCOM recover the fixed costs of power it contracted for an open-access consumer. Captive users do not pay it.

  • Grid & policy

    Group captive

    An open-access structure in which electricity users jointly own at least 26% of a generating plant and consume at least 51% of its output, which exempts that power from cross-subsidy and additional surcharges.

  • Grid & policy

    Open access

    The right to buy electricity from a generator other than your DISCOM, such as an offsite solar farm, and have it delivered over the grid for a set of network charges and surcharges.

  • Grid & policy

    Wheeling charges

    What you pay the distribution company for carrying open-access power over its network from the generator to your factory, usually per unit, plus a share of energy lost on the way.

Keep reading

Free feasibility study

Ask what the surcharge means for your case

The feasibility study is free, takes 7 days and carries no commitment. An engineer replies within 48 hours.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study