Project · Himachal Pradesh

Pidilite – Kala Amb: 205 kWp metal sheet rooftop solar in Himachal Pradesh

Generating since Jan 2026. Pidilite bought the plant under CAPEX and owns it. It is one of 5 Pidilite plants on our project list.

Capacity
205 kWp
Installation
Metal sheet roof
Location
Kala Amb, Himachal Pradesh
Finance model
CAPEX

This plant at a glance

Client
Pidilite
Industry
Chemicals
Capacity
205 kWp (DC), with 175 kW (AC) of inverters
Service
EPC + O&M
Commissioned
Jan 2026
Status
Operational. Built and maintained by Adhvanik Energy; owned by the client.

205 kWp is mid-sized for the list, enough to span a production hall or two. 175 kW of inverters serve 205 kWp of modules: a DC/AC ratio of 1.17.

Running since Jan 2026, the plant has been through a summer and a monsoon. Its seasonal pattern is now visible. Jan 2026 fell in the low-sun winter months.

Closest in capacity on the list: MYK Laticrete – Sotanala (201 kWp, Rajasthan). Britannia – Guwahati (1,700 kWp, Assam) and Mahyco – Jalna (1,119 kWp, Maharashtra) were also commissioned in Jan 2026. In Himachal Pradesh, in order of commissioning, Pidilite – Baddi, 227 kWp comes before it and Pidilite – Kala Amb, 537 kWp after.

Engineering

How a 205 kWp plant is put together

Putting 205 kWp on sheet means respecting a roof built to keep rain out and carry little else. The rails spread the array's weight across several purlins, and the design is checked against wind uplift for the site.

The layout in Kala Amb is drawn around ventilators and skylights, which keep their access and stay out of the modules' shade. A shed roof is often long and clear in one direction, which allows straight rows and short cable runs to the LT panel.

A plant in Kala Amb is only as good as its upkeep: inspections of connectors and inverters, cleaning that follows the local dust, and Asset Connect alerts on a string that has gone quiet.

Finance model

How the plant is paid for

CAPEX is the model where the client buys the plant. For Pidilite – Kala Amb, that means the 205 kWp system is the client's property since Jan 2026, with the savings and the upkeep decisions on the client's side.

A finance head weighing CAPEX against a PPA asks how much capital to commit, how long the plant will run and who will look after it.

Kala Amb

Chemicals plants in Himachal Pradesh

Solar resource here
1,752 kWh/m² a yearAbout 1,531 kWh per kWp a year for a standard tilted system; January is the weakest month. Global Solar Atlas estimate for Kala Amb; a roof plant at roof tilt differs.
Capacity range
Under 250 kWp205 kWp here. 33 plants on our list are in this range.
Type of installation
Metal sheet roofThe most common factory roof.
Finance option
CAPEXThe factory owns the plant from day one.

Besides the plant, our list has 2 other plants in Kala Amb. Its one named sector is chemicals.

Kala Amb is covered on the page for Baddi and Kala Amb, which lists 6 plants.

In Himachal Pradesh the list shows 7 projects in 3 towns. Named sectors include chemicals, FMCG and pharma.

Chemical works run reactors, pumps and utilities through long hours, so daytime demand is high and steady.

The roof assessment checks roof exposure to process emissions and the position of vents, which affect module cleaning and long-term soiling.

Projects

More plants near Kala Amb

Also in Kala Amb

Elsewhere in Himachal Pradesh

Other plants on metal sheet roofs

Common questions

Questions about Pidilite – Kala Amb

What does 205 kWp mean for the Pidilite plant?

This Kala Amb plant has 205 kWp of modules (DC) feeding 175 kW of inverters (AC). Modules are quoted in kWp and inverters in kW. The modules exceed the inverter rating by about 17%, a DC/AC ratio of 1.17.

How is the plant at Kala Amb mounted?

The list records a metal sheet roof. On sheet the structure is fixed through the sheet or, for a zero-leakage roof, held by clamps or adhesive, and it is designed for the wind speed under IS 875.

Is Kala Amb within your reach for a new plant?

Yes. 3 plants are listed for Kala Amb, among 7 in Himachal Pradesh. The free 7-day feasibility study needs only your town and a typical monthly bill.

Free feasibility study

Find out what your sheds can carry

Tell us the roof type and last year's bills. An engineer gets back within 48 hours. The 7-day feasibility study costs nothing.

Call us+91 22 4618 3484Get a free feasibility study