Contract demand

Contract demand is the maximum power, usually in kVA, that a high-tension (high-voltage) consumer agrees with its distribution company (DISCOM) to draw; a share of it sets the floor for demand charges on every monthly bill.

Contract demand and sanctioned load

Sanctioned (or connected) load is the total rating of the equipment your connection is approved for. Contract demand is the most power you have agreed to draw at any one moment, measured as the highest average over a short metering interval set in your tariff. A plant with a large connected load can have a much lower contract demand, because its machines never all run at full power together.

How the demand charge is worked out

Each month your DISCOM bills you on your billing demand: the higher of the maximum demand your meter recorded and a minimum share of your contract demand. That share is set in your state's tariff order; Kerala's tariff for extra-high-tension industry, for example, uses 75%. So a factory that rarely reaches its contract demand still pays for most of it. Because demand is billed in kVA, a poor power factor raises it too.

Why solar alone rarely cuts demand charges

Rooftop solar reduces the units you buy, which lowers the energy charge. It does much less for the demand charge, because the month's peak is often set on a cloudy afternoon or during a night shift, when the plant produces little. To lower billing demand you need to lower that peak: a battery that discharges at peak times, load scheduling, or a better power factor. Solar also matters to contract demand in two other ways: state rules may tie the rooftop capacity you can connect to your sanctioned load, and open-access eligibility is set by contract demand.

Illustrative example

Worked example: right-sizing contract demand

A factory with a 1,000 kVA contract demand whose meter recorded a 700 kVA maximum this month, in a state that bills at least 75% of contract demand.

Floor: 75% of 1,000 kVA
750 kVA
Billing demand
Higher of 700 and 750 = 750 kVA
Demand charge at ₹400 per kVA
₹3,00,000
After reducing contract demand to 850 kVA
Floor 637.5 kVA, so billing demand = 700 kVA, charge ₹2,80,000

Saving: ₹20,000 a month, before any solar, from a contract demand that matches real use.

Illustrative numbers. Reducing contract demand needs DISCOM approval, and excess-demand penalties apply if you then go over it.

What to review on your bills

  • Recorded maximum demand for each of the last 12 months, against your contract demand
  • The minimum billing share in your tariff, and any excess-demand penalties paid
  • Your average power factor, and any penalty or incentive for it
  • When in the day the monthly peak is set, and whether solar or storage could cut it
  • Your state's process and notice period for revising contract demand

Batteries and billing demand

Our battery storage work is built for peak shaving and demand-charge reduction, and for firm power. A battery that discharges at the monthly peak is the most direct way to lower billing demand.

See battery energy storage

Sources

  1. KSEB tariff schedule: demand charged on the higher of recorded maximum demand or 75% of contract demand (opens in a new tab)
  2. Mercom: consumers with aggregate demand of 100 kW can avail green energy open access (opens in a new tab)

Related terms

  • Your power bill

    Sanctioned load

    The total connected load, in kW or kVA, that your DISCOM has approved for your connection. State rules often use it to cap how much rooftop solar you can connect.

  • Your power bill

    Peak shaving

    Cutting the highest point of your demand, usually with a battery or load scheduling, to lower the demand charge on your bill and avoid peak-hour tariffs.

  • Your power bill

    ToD tariff

    Time-of-day tariff: electricity priced by the hour of use, at least 20% cheaper in the state's solar hours and at least 20% dearer in peak hours for industry.

  • Equipment & O&M

    BESS

    Battery energy storage system: batteries with their own inverter and controls that store energy and release it later, used in industry mainly to cut peaks and back up critical loads.

Keep reading

Free feasibility study

Ask us to read your bills for contract demand

The feasibility study is free, takes 7 days and carries no commitment. An engineer replies within 48 hours.

What the study covers

  • Financial ROI sheet based on a preliminary design
  • Policy check for your state and connection
  • Roof feasibility and the area available for installation
Call us+91 22 4618 3484Get a free feasibility study